eSmart Networks was appointed to provide the capability for RATP Dev Transit London to run new electric bus routes from their Edgware Garage.
This required the construction of a bespoke brick-built substation including a 3-panel switchboard for DNO (UKPN) adoption.
Provision of a privately owned 1.5MVA transformer supplying a 2.5kA switch panel distributing power to 19 BYD 80kW AC charging outlets and 2 ABB 180kW DC Fast Chargers along with the installation of supporting infrastructure and containment, installed in the environment of a busy working bus Garage. Retro-fit works of this nature require extensive planning and close interaction with the client and installation team to keep efficiency high and client site disruption low.
Furthermore, our civil design, electrical design, and operational teams demonstrated their multi-disciplinary talent in overcoming these complex electrical, civil, and practical challenges.
Read the full case study here. Or take a look at our other works via our Case Studies page.
Follow our social media pages for more updates:
Instagram: https://lnkd.in/e-rpys3g
Twitter: https://lnkd.in/diWm9pAv
YouTube: https://lnkd.in/dibF22jg
The Grid Podcast
The electricity grid is at the centre of the energy transition, and our journey to net zero by 2050. Join us for an exciting ride!