Peterborough Mandolin, 33kV Primary Substation

eSmart Networks were appointed to deliver a full turnkey ICP design and build contract, following our initial grid consultancy work which helped the client relocate from a heavily constrained site in Birmingham to a viable connection opportunity in Peterborough. Our team worked closely with the DNO to fast-track the connection strategy, delivering a phased capacity plan that enabled early energisation and supported the client’s critical manufacturing timelines.

Back to Case studies

Project overview

eSmart Networks was appointed as the ICP (Independent Connection Provider) to deliver a full turnkey grid solution for a major manufacturing site in Peterborough, including a new 33/11kV primary substation and extensive off-site cabling.

    • We delivered the full design, procurement, installation, and commissioning of a 2km off-site 33kV cable route, a new 33/11kV primary substation (including civils), and a downstream 11kV & secondary substation network, supported by an IDNO-enabled solution to reduce CAPEX.
    • Our team carried out detailed cable route design and traffic management coordination, while also developing the on-site 11kV private network and six package substations.
    • eSmart Networks managed all DNO interfaces and accelerated delivery through a phased connection plan, enabling early energisation and ramp-up of the customer’s manufacturing operations.

Challenge

  • The original preferred site in the Birmingham area faced severe grid constraints, with DNO reinforcement works resulting in connection lead times exceeding five years.
  • Even at the alternative Peterborough site, full capacity was dependent on long lead-time DNO upgrades, particularly the installation of a new 33/11kV transformer.
  • The project had a tight manufacturing programme that relied on early power availability, requiring a flexible and fast-tracked connection strategy to avoid critical delays.

Solution

  • Our Grid Consultancy team identified Peterborough as a viable alternative connection point and secured capacity through a strategic review of the DNO’s upcoming infrastructure upgrades.
  • We developed and implemented a phased energisation strategy, enabling power availability to ramp up in line with the client’s operational milestones—starting with 5.5MVA via the local 11kV network, progressing through interim stages, and reaching full 12.5MVA capacity as DNO works completed.
  • eSmart Networks took full ownership of the DNO interface, ensuring clear communication, risk mitigation, and delivery alignment throughout the project lifecycle.
Under 3 Years
Full connection achieved—fast-tracked from original 5-year forecast
2km
Off-site 33kV cable route installed
1
New 33/11kV primary substation designed and installed

How we helped

We combined grid consultancy with full turnkey delivery to fast-track the project. By managing the DNO interface and implementing a phased connection plan, we reduced costs and enabled early energisation to meet the client’s critical timelines.